Roof Photos must be submitted when on-site.
Dektite must be positioned above the top rail and underneath the panels. Conduit metal cable-tied to the rail.
Photo of the completed install taken on the roof
Photo of the completed install taken from on the ground
Regulations require the conduit to be more than 50mm below the roof underside, and more than 600mm above the ceiling (unless within 1 metre of the external wall). Drops into the HWC must be vertical from the rafters.